Coast Guard Headquarters/St. Elizabeths Campus
Total
Description

Comprised of an 11-story office building, utility plant, and two sevenstory parking garages, the new 1.2 million square-foot U.S. Coast Guard Headquarters campus required an immense excavation and massive support of excavation, deep foundation, and global stability systems. The scope of work for this project required removal of 2.4 million cubic yards of soil within a 1-year schedule for our work. This project is one of the largest excavations ever completed in Washington, D.C. Further complicating this task, large amounts of soil were contaminated or classified as hazardous materials requiring special considerations. Nine different soil types were transported to more than 12 different disposal facilities, four of which were over 100 miles from the site. Further complicating the job is the 120-foot change in elevation and unstable soil conditions revealed in early geotechnical reports. Sixty percent of the support of excavation scope was located below one million cubic yards of excavated earth, requiring close coordination with the sheeting and shoring operations. Our teams worked in two shifts and, at the height of the project, moved over 12,000 cubic yards of soil daily to ensure timely project delivery

Subcontracted Work

90% of this contract was self-performed by Total. The balance of the work was subcontracted to major trades including: asphalt paving, site concrete, and demolition.

Cost And Time Growth Discussion

The difference in cost was due to Owner directed changes resulting from 700,000 ton of contaminated soils from over 10 sources.

Offeror's Role

Our role in this project was a Subcontractor for Clark Construction and GSA. The scope of our work included all site demolition and excavation including:

  • > Clear and grub
  • > Building/Surface Demolition
  • > Erosion and sediment controls
  • > Excavation of approximately 2,400,000 CY
  • > Grading of all paved areas, hardscape, earth berms, and bridge approaches
  • > Contaminated soil removal and disposal
  • > Utility installations including
  • > Hazardous material removal and disposal
  • > Access Service Roads
  • > Soil Stabilization for roadway by stone bridge lift for CL soil
Location
Washington, DC
Project Owner

General Services Administration / St. Elizabeths Campus

Shapour Ebadi 10903 New Hampshire Ave Silver Spring, MD 20903 (ph) 301-572-6866 (fax) 301-572-4672

Schedule

Start Date: February 1, 2010

Original Completion:
February 1, 2012

Final Completion
December 31, 2011

Months: 22

GSF/Mon: N/A

Cost

Original Cost: $24,150,000

Final Cost:$61,368,671

%Difference: 254%

%Gsf: N/A

Project Owners Acquisition Methodology

Delivery: Bid-Build

Procurement: Best Value Selection

Contracting: Lump-Sum

Bim Usage

Design: Yes

Construction: Yes

Related Projects
  • 9344 Lanham Sevem Road, Suite 210 Lanham, MD 20706
  • Call us: 301 459 7484
  • Call us: 703 928 8746
  • E-mail: contact@tcce.biz

Copyright 2014 :
Total Civil Construction