Construction of a new loop road for the FDA White Oak Campus and all associated sitework for the new campus buildings of CDER II, Southwest Parking Garage, CDRH, OC/ORA, and Building 1. Construction consisted of building & surface demolition; roadways; earthwork; building pad mass excavation; utility relocation for: electrical distribution, telecommunication distribution, waterlines, and sanitary sewer systems; storm water management piping and systems; and contaminated soil abatement.

Subcontracted Work

100% of this contract was self-performed by Total

Cost And Time Growth Discussion

The added cost to our contract amount was the result of unforeseen change conditions encountered during excavation for our work. The changes included unsuitable soils, utility conflicts/relocations, and contaminated soil abatement. Additionally, the Owner elected to increase the original scope of ou

Offeror's Role

Our role in this project was a subcontractor for GSA. The scope of our work included all roadway construction, utility installations, and associated site work including

  • > Clear and grub
  • > Building/Surface Demolition
  • > Erosion and sediment controls
  • > Excavation of approximately 270,000 CY
  • > Grading of all paved areas, building pads, hardscape
  • > New roadway and parking areas
  • > Utility installations including:
    • Storm Drain RCP pipe ranging from 12" to 60”
    • DIP water pipe ranging from 8” to 12”
    • PVC sewer pipe ranging from 6” to 12”
    • Electrical/Telecommunication ductbank relocation/support for new work installation
    • Jack and bore as required under existing facilities
  • > Bioretention Ponds
  • > Soil Stabilization of 24,000 SY for roadway by stone bridge lift for ML soil
  • > Multiple storm water management ponds and all associated culverts and structures
  • > Contaminated soil abatement
Location
Silver Spring, MD
Project Owner

General Services Administration / FDA White Oak Campus

Shapour Ebadi 10903 New Hampshire Ave Silver Spring, MD 20903 (ph) 301-572-6866 (fax) 301-572-4672

Schedule

Start Date: October 4, 2005

Original Completion:
December 15, 2008

Final Completion
December 1, 2008

Months: 38

GSF/Mon: N/A

Cost

Original Cost: $8,760,706

Final Cost:$10,001,759

%Difference: 114%

%Gsf: N/A

Project Owners Acquisition Methodology

Delivery: CMAR

Procurement: Best Value Selection

Contracting: Lump-Sum

Bim Usage

Design: Yes

Construction: Yes

Related Projects
  • 9344 Lanham Sevem Road, Suite 210 Lanham, MD 20706
  • Call us: 301 459 7484
  • Call us: 703 928 8746
  • E-mail: contact@tcce.biz

Copyright 2014 :
Total Civil Construction